Project Cost - how to increase value limit

Technical Questions
Q. We need to increase the project/activity fixed cost field to allow for a value greater than 100,000.00. When we try to save it, it highlights the project fixed cost box and a little pop up box that says "Billing amount must be a decimal value between 0 and 100000".
How do we get that increased?

A. To change this value find the file App_Data\EntityClasses.config

Find the line and change the default value 100000 of the parameter "MaxValue".

Note that after an upgrade (from the installer) you'll need to check to see that this wasn't reset.