Activity dependency: Link column

Activity Center > Activities


When an activity is in dependency with one or more master ones, e.g. it is set to start in 3 days after the other finishes, the master activity’s ID appears in the Dependency field along with the dependency symbol ().

To edit  the dependency:



Click the dependency symbol (e.g. ).


Make changes, as appropriate.


Click 'Apply'.




In the illustration, ‘Layout’ activity (ID 176) is dependent on ‘Design’ one (ID 104). The ‘104’ next to the dependency symbol points at the ‘Design’ activity as the master one.





Illustration: Task 176 is in a dependency with Task 104.


Dependency on a critical path


When a dependent activity belongs to a critical path, the dependency symbol is yellow.